Step-by-step Overview
Indicative timeframe: 36 - 72 months
Start here
STEP 2
Technical options analysis
- Waste characterisation study
- Technology options screening process
Service delivery options
- Identify if project falls under municipal service or function
- Determine risk retain and transfer
- Consider MSA
Council resolution
Approval to proceed to feasibility
2 - 6 months
STEP 3
Feasibility
- Appoint service provider to determine technical, financial, economic and environmental feasibility
- If PPP (s120) follow National Treasury PPP directives
Council resolution
Approval of feasibility to continue to procurement process
14 - 18 months
STEP 4
Procurement process
- Bid specification
- Bid evaluation
- Bid adjudication
- Special procurement procedures for PPP
- Formulate contracts
- Contract negotiation
- Contract finalisation
12 - 24 months
Contract management and commence construction
- Comply with contractual agreements throughout construction phase
Monitoring and maintenance
- Consider Greenhouse gas emissions
- SAWIS: Capture routine data on the tonnages of waste generated, recycled and disposed on a monthly and annual basis