Step-by-step Overview

Indicative timeframe: 36 - 72 months

 

 

 

Start here

STEP 1

Municipal needs analysis

  • Status quo assessment
  • Prioritise project in IWMP
  • Integrate IWMP with IDP
  • Establish Project Steering Committee (PSC)

3 months

STEP 2

Technical options analysis

Service delivery options

  • Identify if project falls under municipal service or function
  • Determine risk retain and transfer
  • Consider MSA

Council resolution

Approval to proceed to feasibility

2 - 6 months

STEP 3

Feasibility

  • Appoint service provider to determine technical, financial, economic and environmental feasibility
  • If PPP (s120) follow National Treasury PPP directives

Council resolution

Approval of feasibility to continue to procurement process

14 - 18 months

STEP 4

Procurement process

    • Bid specification
    • Bid evaluation
    • Bid adjudication
    • Special procurement procedures for PPP
  • Formulate contracts
  • Contract negotiation
  • Contract finalisation

12 - 24 months

 

Contract management and commence construction

  • Comply with contractual agreements throughout construction phase
 

 

Monitoring and maintenance

  • Consider Greenhouse gas emissions
  • SAWIS: Capture routine data on the tonnages of waste generated, recycled and disposed on a monthly and annual basis

GHG Calculator